Fig. 3.1.8c,d,e,f, In the meantime,
this will be the boatyard (c,d),
... what looked like five days work was actually one month of rather hard
work which we paid dearly for later in winter by delaying the final welding;
at the end we got an 18m long and about 7m wide wind and water-proof,
yet breathable space with about 5m clearance (e).
Drilling
of the 22 holes, 70cm deep and about 40 cm wide, for concrete columns
which will form the basis for the construction rig (f).
|
|
|
|
Dates: 21.5.2004, 30.6.2004, 3.9.2004
and 7.6.2004
Level of optimism: near to zero... worse work, only comparable to building
a space for mechanical workshop... |
|
|
|